TotalEnergies approves Nigeria’s Ima offshore gas development

TotalEnergies and Nigeria’s AMNI approved the Ima gas field near Bonny Island, connecting it by a 22-kilometre pipeline to Nigeria LNG. Start-up is expected in 2028, with planned production of 350 million cubic feet per day.

By DoomRadar · Published on DoomRadar . Updated .

What happened

TotalEnergies, which will operate the project with a 40% interest, and Nigerian partner AMNI, which holds 60%, took the final investment decision for the Ima gas field. [1][3]

References for this detail (2)

Production start-up is expected in 2028, with a planned plateau of 350 million cubic feet per day. [1][3][2]

References for this detail (3)

Context from the sources

The project is intended to increase supply for Nigeria’s expanding LNG export plant, according to reporting on TotalEnergies’ decision. [2]

Explore the sources and reporting timeline

3 source links · 3 domains

These counts describe the references, not independent confirmations. Different outlets can repeat the same original report.

Source timeline

Oldest to newest among the available source dates, not a chronology of the incident. Article publication dates come from the source; other recorded dates may reflect when a link was found.

  1. Recorded source date: Sep 23, 2026, 7:02 AM UTC[1] TotalEnergies SE: Nigeria: TotalEnergies Launches the Ima Gas Development to Supply Nigeria LNG Liquefaction Plantfinanznachrichten.deReferenced for: detail 1, detail 2, detail 3, detail 4
  2. Recorded source date: Sep 23, 2026, 8:31 AM UTC[3] Nigeria: TotalEnergies launches the Ima Gas Development to supply Nigeria LNG liquefaction plantenergy-pedia.comReferenced for: detail 1, detail 2, detail 3, detail 4
  3. Recorded source date: Sep 23, 2026, 12:16 PM UTC[2] TotalEnergies to Develop Offshore Gas Field to Boost Nigeria LNG Supplyoilprice.comReferenced for: detail 4

What this could mean for you

Energy bills

A delayed or incomplete project could postpone the additional gas supply intended for Nigeria LNG.

The planned supply depends on building the offshore platform and 22-kilometre pipeline and bringing the field online.

Reported basis: [1][3] · The possible effect is interpretation.

Depends on: Construction, connection and commissioning fail to meet the expected 2028 start-up.

Possible time frame: months, if those conditions hold.

Possible consequences, not a forecast. Their relevance depends on your location and the conditions above.

For your country

Choose a country to check how this event could affect you.

What changes the outlook

Risk increases if…

Construction or commissioning misses the expected 2028 start-up.

Pressure eases if…

The platform and pipeline are completed and connected to Nigeria LNG as planned.

Still unclear

The sources do not provide a construction schedule, financing amount or confirmed completion date beyond the expected 2028 start-up.

The sources do not establish how much Nigeria LNG’s export capacity or domestic gas availability would change.

Market implications

Market impact

Loading market analysis...
Sources (3)

References for the reported details. Separate links do not necessarily mean independent confirmation.

[2] TotalEnergies to Develop Offshore Gas Field to Boost Nigeria LNG Supply ↗oilprice.com · Recorded source date: Sep 23, 2026, 12:16 PM UTC
Available excerpt
TotalEnergies has decided to invest in the development of the Ima gas field offshore Nigeria to increase supply for the expanding Nigeria LNG export plant,…